Filing a New York Mechanic’s Lien for Unpaid Private Construction Work

A New York contractor, subcontractor or supplier may be able to use a mechanic’s lien to secure an eligible claim on a private improvement. The project type, claimant’s role, last qualifying work and filing and service dates can control the result. Confirm those facts before treating a lien as available.

Calendar filing, service and continuation separately

New York Lien Law § 10 generally permits filing during the work or within eight months of the relevant statutory event for many private improvements. The period is generally four months for a single-family dwelling improvement, subject to the statutory details. Use the dates the law recognizes. A later visit for minor corrective work should not be assumed to restart the clock.

Section 11 generally requires service of the lien notice on the owner within the period from five days before filing to 30 days after filing. It separately requires filing proof of service within 35 days after filing the notice. Section 17 generally provides a one-year duration unless steps required by law are taken. Foreclosure, a notice of pendency and any extension require their own review.

Confirm the property and the amount

Collect the signed contract, change orders, delivery receipts, time records, invoices and payments. Verify the owner and property description against public records. Identify who authorized extra work and whether the claimed amount includes disputed items. A subcontractor should also examine issues that can arise from payments between the owner and general contractor.

A public improvement follows a different procedure. Check the project classification and whether another remedy, such as a contract claim, may be available.

What to gather for review

  • Owner record and property identifier
  • Evidence of the last qualifying work or delivery
  • Separate calendar for filing, service and lien continuation

What should a contractor provide for review?

Share the project address, scope, last dates of labor or delivery, signed documents and the outstanding amount. Arkady Bukh Law Firm can evaluate lien eligibility, deadlines and related collection options.

Related resources  Construction litigation  ·  Commercial litigation

Legal sources  New York Lien Law § 10  ·  New York Lien Law § 11  ·  New York Lien Law § 17